Ventnor Beach replenishment project to start later this month

Posted: Updated:
VENTNOR - A beach replenishment project in Ventnor is set to get underway later this month.

The project was originally scheduled to start at the end of September, but equipment breakdowns and bad weather like Wednesdays's impeding storm have pushed the start date back to October 22nd.

The Army Corps of Engineers will pump nearly 530 cubic yards of sand onto a mile and a half of the city's beaches, raising them 5 feet.

Dune crossovers will also be restored to the pre-Hurricane Sandy levels.

The project is expected to take 30 days to complete.